Corporate Ispat to set up steel plant in Jharkhand.

Company Name : Corporate Ispat Alloys
Project Status : Implementation
Project Location : Jamshedpur, JH
Project Cost : Rs.100,000 million
Completion Schedule : 2012

Corporate Ispat Alloys, a unit of Abhijeet group is setting up a 2-million tonne steel plant in at Kharswan, Jamshedpur.
The project coming up in an area of 4,000 acres is likely to cost Rs.100,000 million.
As of [...]

Corporate Ispat Alloys to set up a Thermal Power Plant.

Company Name : Corporate Ispat Alloys
Project Status : Planning
Project Location : Burdwan, WB
*Corporate Ispat Alloys is planning to set up a 10 MW Biomass Based Thermal Power Plant at Banskopa in Durgapur in Burdwan district of West Bengal.
*Total land requirement is 15 acres.
*As of August 2009, the project has obtained clearance from ministry of environment [...]

Corporate Ispat Alloys reports progress on Steel Project.

Company Name : Corporate Ispat Alloys
Project Status : Implementation
Project Location : Kharswan, JH
Project Cost : Rs.90,000 million
Completion Schedule : 2 years
•              Corporate Ispat Alloys , belonging to Abhijeet Group has reported progress on its integrated steel plant project coming up in Jharkhand.
•              The project involves setting up a 2.5 million tpa integrated steel plant in [...]

Corporate Ispat Alloys to set up integrated steel plant in Jharkhand.

Company Name : Corporate Ispat Alloys
Project Status : Planning
Project Location : Saraikela, JH
Project Cost : Rs.91200 million

•              Corporate Ispat Alloys is planning to set up an integrated steel plant and a captive power plant at Village Mahali Murup in Saraikela – Kharswan district of Jharkhand.
•              The project involves setting up a 2.5 MTPA integrated steel [...]

Corporate Ispat Alloys is setting up a

Company Name : Corporate Ispat Alloys
Project Status : Implementation
Project Location : Burdwan, WB
Project Cost : Rs.89.61 crores
Corporate Ispat Alloys is setting up a captive power plant in WB. The project involves setting up of a 20 MW coal based captive power plant at Durgapur, West Bengal. The land requirement for the project is 16 acres. [...]