Parbati – II Hydel Project – Current Status

May 31, 2007 by Prakash  
Filed under Energy, Hydel Power

National Hydro Electric Power Corp has reported progress on its 4 x 200 MW Parbati – II Hydel project in Himachal Pradesh. The project was initiated in September 2002.
Current Status :
Dam- 85 m high concrete Gravity: Excavation completed. 80010 cum Dam & Inlet structure concreting out of 188609 cum completed.
Head Race Tunnel- 6 [...]

Continue Reading...

Arasmeta Captive Power to Double Capacity

May 30, 2007 by Prakash  
Filed under Captive Power, Energy

Arasmeta Captive Power , a subsidiary of Cement major Lafarge India is planning to expand its captive power plant by two fold. The project involves setting up a 1×43 MW Coal Based Thermal Power Plant in addition to its existing unit of similar capacity at Gopal Nagar in Champa district of Chhattisgarh. As of May [...]

Continue Reading...

Suryadev Alloys Plans Mini Steel Plant in TN

May 30, 2007 by Prakash  
Filed under Metallurgical Industries

Suryadev Alloys & Power is planning to set up a Mini Steel Plant with a capacity to produce 140,000 tpa of rolled products at Gummidipoondi in Thiruvallur district of TN. As of May 2007, the project has obtained clearance from ministry of environment and forests.
Suryadev Alloys & Power Pvt Ltd, 17/12 New Vaidyanathan [...]

Continue Reading...

Next Page »